Swing Bridge Repairs 2011
Nottingham Canal Swing Bridge at Great Northern Basin
The 2011 restoration work entailed the removal of the planking, bearers, and ballast, then cleaning, repairing, and painting the frame. The bearings and pintle were also cleaned and fitted with a cover. The new bearers and planking were then installed and following slight adjustment to the ballast the bridge was re-opened.